LIST OF CONSTRUCTION COMPLETION DOCUMENTS EFFECTIVE FROM 01/7/2026

·Policy & Regulation Updates

Government Decree No. 207/2026/ND-CP, dated June 15, 2026, takes effect on July 1, 2026. Under Article 28 and Appendix VII, construction completion dossiers (commonly referred to as as-built documentation) are divided into three main categories.

Below is the complete list translated from Appendix VII, with the original structure and content preserved.

1. List of Documents in a Construction Completion Dossier

(Attached to Government Decree No. 207/2026/ND-CP dated June 15, 2026)

I. CONSTRUCTION INVESTMENT PREPARATION DOCUMENTS AND CONTRACTS

1. Decision on construction investment policy and Pre-Feasibility Study Report for construction investment (if any).

2. Decision approving the construction investment project and Feasibility Study Report or Economic-Technical Report for construction investment.

3. Design brief; documents on appraisal and opinions provided by relevant authorities during the appraisal of the construction investment project and basic design.

4. Compensation, site clearance, and resettlement plans (if any).

5. Documents issued by competent organizations and state authorities (if any) regarding: planning agreements; agreements or approvals for the use of or connection to technical infrastructure outside the project boundary; environmental impact assessment; safety assurance (traffic safety and safety of adjacent structures); and other relevant documents.

6. Decisions on land allocation or land lease issued by competent authorities, or land lease agreements in cases where land is not allocated.

7. Construction permits, except for cases exempt from construction permit requirements.

8. Decisions on direct contractor appointment, approvals of contractor selection results, and construction contracts between the project owner and contractors.

9. Documents proving contractors' qualifications and capacity as required by regulations.

10. Other relevant documents and records during the construction investment preparation stage.

II. CONSTRUCTION SURVEY AND DESIGN DOCUMENTS

1. Survey brief, survey technical plan, and construction survey results report.

2. Written approval of the construction survey results report, where approval is not given directly on the report.

3. Results of construction design verification and appraisal; decisions approving the construction design, accompanied by the approved construction design documents (including a list of drawings) and technical specifications.

4. Written notice of acceptance of the construction design.

5. Other relevant documents and records related to the construction survey and design stage.

III. CONSTRUCTION MANAGEMENT DOCUMENTS

1. List of design changes made during construction, together with appraisal and approval documents issued by competent authorities.

2. As-built drawings (including a list of drawings).

3. Plans and measures for inspection and quality control during construction.

4. Certificates of origin, product labels, documents declaring applicable standards for products and goods; certificates of conformity with technical regulations, declarations of conformity with technical regulations, notices of receipt of conformity declaration dossiers issued by specialized authorities; and certificates of conformity with standards (if any), in accordance with the Law on Product and Goods Quality.

5. Monitoring results (if any), measurements, and test results obtained during construction.

6. Records of acceptance of construction works, and acceptance of construction components or stages (if any) during construction.

7. Results of verification tests, construction quality inspections, and structural load-bearing capacity tests (if any).

8. Quality management documents for equipment installed in the construction works.

9. Procedures for operation and use of the construction works (if any), and maintenance procedures.

10. Agreements, approvals, and confirmations issued by competent organizations and state authorities (if any) regarding:

a. Relocation of residents from reservoir areas and surveys of historical and cultural heritage sites;

b. Fire prevention and firefighting safety;

c. Environmental safety;

d. Occupational safety and safe operation of building equipment systems and technological equipment;

e. Compliance with construction permits (where a construction permit is required);

f. Permission to connect to technical infrastructure and other relevant works;

g. Documents issued by specialized construction authorities and urban development management authorities regarding the completion of relevant technical infrastructure works of the project in accordance with the construction schedule specified in the appraised and approved Feasibility Study Report;

h. Other documents required by relevant laws.

11. Documents relating to the handling of construction incidents (if any).

12. Appendix listing outstanding defects requiring repair or correction (if any) after the construction work or work item has been put into use.

13. Records of acceptance of completed construction works or work items.

14. Written notices issued by competent authorities as prescribed in Clause 4, Article 57 of Construction Law No. 135/2025/QH15 (if any).

15. Relevant documents and records prepared during the inspection of construction acceptance activities in accordance with regulations (if any).

16. Other relevant documents and records relating to the construction and acceptance stages.

2. Key Notes on Preparing and Retaining Construction Completion Dossiers

Under Article 28 of Decree No. 207/2026/ND-CP, project owners and other parties involved in construction should pay attention to the following requirements:

  • Responsibility for dossier preparation: The project owner is responsible for organizing the preparation of the construction completion dossier after the completed construction work or work item has been accepted, and for ensuring the accuracy and truthfulness of the dossier. Contractors are responsible for the documents they prepare.
  • Language: The dossier must be prepared in Vietnamese. For projects involving foreign parties, the parties may agree to use English or another foreign language in addition to Vietnamese.
  • Scope of dossier preparation: A single dossier may be prepared for the entire project if the construction works or work items are put into use at the same time. If they are put into use at different times, separate dossiers may be prepared.
  • Document retention: The project owner is responsible for preparing and retaining one set of construction completion documents. Other participating parties must retain documents relating to their respective work. Documents must be retained in original and electronic copy formats in accordance with regulations.

3. Important Considerations When Applying the Document Checklist

Not every construction project requires all the documents listed above. The required documents should be determined based on the type of construction works, investment scope, procedures completed, and the applicable requirements for each document.

For project owners, construction supervision consultants, and construction contractors, collecting, reviewing, and retaining documents throughout project implementation can help prevent missing documentation during completion acceptance, handover, and commissioning.

The checklist in Appendix VII should also be reviewed together with relevant regulations on construction quality management and acceptance to ensure that the completion dossier meets the requirements applicable to each specific project.